Unternehmensachen Ungefähr Delivering 24 Three-Phase Pad-Mounted Transformers (Up to 7MVA) in 50 Days for a U.S. Distribution Project
Delivering 24 Three-Phase Pad-Mounted Transformers (Up to 7MVA) in 50 Days for a U.S. Distribution Project
2026-11-24
When a U.S. industrial and commercial distribution project required 24 three-phase pad-mounted transformers across three distinct capacity ratings—all on a single, tight 50-day delivery schedule—Winley Electric engineered a compact, multi-voltage solution and executed parallel production lines to deliver every unit on time.
-
24 Units Manufactured & Tested
-
3 Capacity Groups Up to 7000kVA (ONAF)
-
8 Primary Voltages Configurable per Unit
-
50-Day Total Production Cycle
| Specification | Project Details |
| Application | U.S. Outdoor Medium-Voltage Industrial & Commercial Distribution |
| Product Type | Three-Phase Oil-Immersed Pad-Mounted Transformers (Radial Feed) |
| Ratings & Quantities |
• 2550kVA × 10 units • 3000 / 3750 / 4200kVA × 4 units • 5000 / 6250 / 7000kVA (ONAN/ONAF) × 10 units |
| Secondary & Frequency | 480V Delta, 60Hz |
| Primary Tap Settings | 8 De-energized Voltages: 12.47, 13.2, 13.8, 22.86, 24.94, 26.4, 33, and 34.5kV |
| Standards & Compliance | IEEE C57.12.00, IEEE C57.12.34, UL Listed (File E536138) |
![]()
![]()
-
Extreme Low-Voltage Current Density: Stepping down to 480V at a 7MVA peak load generates approximately 8420A on the secondary side—demanding rigorous thermal management and busbar layout to prevent localized overheating.
-
Strict Site Footprint Limits: The largest 7MVA units had to fit an existing 83.0 × 31.4 in. concrete pad opening while preserving full front-access clearance for high- and low-voltage cables.
-
Fleet-Wide Voltage Standardization: The buyer needed every transformer across all three capacity groups to support eight different primary distribution voltages (12.47kV to 34.5kV) to simplify site spares and field deployment.
To achieve 7MVA capacity within the customer's dimensional envelope, Winley engineered a rear-mounted radiator and forced-air cooling architecture (ONAN/ONAF) equipped with dual 480V cooling fans and an integrated control box. Placing the entire cooling assembly at the rear kept the front high- and low-voltage compartments unobstructed for safe cable termination and field maintenance.
![]()
![]()
Rather than building the three capacity groups sequentially, Winley ran parallel production workflows across all three ratings to deliver the entire 24-unit order within 50 days.
Winley wound high- and low-voltage coils simultaneously across all three capacity groups to match project drawings, supporting eight-position de-energized tap configurations and high secondary current ratings.
![]()
Silicon steel cores were stacked around the wound coils with precision clamping to control no-load losses and noise, followed by thermal drying to prepare the active parts for tanking.
![]()
Tank procurement and arrival schedules were aligned with active-part completion dates for each capacity group so dried cores could move straight into tanking without bottlenecking.
![]()
Once seated in the tank, the unit undergoes vacuum drying/degassing and transformer oil filling so the core and coil insulation system are fully impregnated under controlled conditions, eliminating trapped air pockets and moisture.
![]()
Technicians fit the front high- and low-voltage cable compartments and—on the largest units—install the rear radiator banks, dual 480V fans, and dedicated fan-control box per the general arrangement drawing.
![]()
Every single transformer underwent full routine testing per IEEE standards prior to release, with serialized test reports traceable to each unit's nameplate. Across all 24 transformers, the maximum absolute voltage ratio deviation across all eight tap positions was just 0.38%—well within the IEEE tolerance of ±0.5%.
| Base Rating (ONAN) | Qty | Measured No-Load Loss | Measured Load Loss (85°C) | Short-Circuit Impedance | Max Ratio Deviation |
| 2550kVA | 10 | 2093–2194 W | 16824–18446 W | 5.79%–6.07% | 0.30% |
| 3000kVA | 4 | 2608–2673 W | 18836–19694 W | 5.77%–5.84% | 0.17% |
| 5000kVA | 10 | 3924–4185 W | 33925–35773 W | 6.01%–6.58% | 0.38% |
All 24 units also passed induced voltage withstand, separate-source dielectric withstand, and tank pressure integrity tests with zero leaks or insulation defects.
![]()
With 24 large pad-mounted transformers—including 7MVA units—shipping overseas, proper moisture protection and load securing are critical to preventing transit damage.
-
Moisture & Impact Protection: Each transformer was mounted on a reinforced wooden skid and fully wrapped in protective cushioning foam and stretch film to guard against coastal humidity and abrasion during ocean transit.
-
Heavy-Duty Container Securing: Units were loaded directly inside our workshop and anchored to the container floor lashing rings using industrial ratchet tie-down straps to prevent shifting at sea.
-
Coordinated Fleet Dispatch: Multiple 40-foot high-cube containers were loaded and dispatched in sequence from our facility to keep the full 24-unit shipment on schedule.
![]()
Delivering 24 custom pad-mounted transformers across three capacity ratings up to 7MVA in 50 days reflects how Winley Electric executes complex, multi-specification orders—combining custom thermal engineering, parallel workshop scheduling, and serialized IEEE routine testing under one roof.
-
Engineered for Tight Footprints & High Currents: From UL-listed pad-mounted designs (File E536138) to IEEE C57.12.00 / C57.12.34 compliance, our engineering team adapts cooling layouts, multi-tap configurations, and compartment dimensions to fit existing site pads while safely handling high secondary current loads.
-
Parallel Production for Compressed Lead Times: Multi-line scheduling keeps different kVA ratings moving simultaneously across winding, core stacking, vacuum oil filling, and final assembly—allowing buyers to track one unified delivery schedule across an entire mixed-rating order.
-
100% Serialized Traceability & Factory Verification: Every unit undergoes full routine testing prior to shipment, backed by a serial-numbered test report verifying voltage ratio accuracy across all tap positions, measured losses, dielectric withstand, and tank pressure integrity.