I. Project Overview

 

  • Quantity: 153 units of single-phase pole-mounted transformers
  • Delivery Time: 7 weeks (from order confirmation to container loading)
  • Target Standard: Compliant with Canadian CSA C2.2:06
  • Certifications: UL / cUL (for Canada & North American market access)
  • Transportation: Factory in China → Sea freight to Canada

 

aktueller Firmenfall über [#aname#]

 

II. Winley's Solutions & Product Advantages (Canada-Ready)

 

1.Full-Specification Alignment with Canadian Power Grid

 

All 153 units are single-phase, 60Hz, outdoor pole-mounted transformers, covering three core capacities (15kVA/25kVA/50kVA) to perfectly fit residential areas, commercial streets, rural power grids, and new energy grid connection points:

  • 15kVA (13856GrdY/8000V) → 120/240V
  • 15kVA (Dual-Voltage Compatible) → 120/240V
  • 25kVA (Dual-Voltage Compatible) → 120/240V
  • 25kVA (13856GrdY/8000V) → 120/240V
  • 50kVA (13856GrdY/8000V) → 120/240V
  • 50kVA (24940GrdY/14400V) → 120/240V

 

aktueller Firmenfall über [#aname#]

 

aktueller Firmenfall über [#aname#]

 

aktueller Firmenfall über [#aname#]

 

2. UL/cUL + CSA C2.2:06 Dual Certification – Accessible Across North America


Winley Electric's pole-mounted transformers hold complete UL and cUL certification qualifications, complying with UL 1561 and IEEE C57 series standards, while strictly meeting Canada's CSA C2.2:06 requirements:
Full compliance in insulation system, temperature rise, short-circuit withstand capacity, voltage resistance, and mechanical strength
Direct grid connection, inspection, and insurance eligibility; no customs clearance or acceptance risks
Single product meets access requirements for both U.S. and Canadian markets

 

aktueller Firmenfall über [#aname#]  aktueller Firmenfall über [#aname#]

 

3. 7-Week Fast Delivery


Only 7 weeks from order confirmation to container loading, demonstrating strong supply chain and production efficiency(including design confirmation, material preparation, manufacturing, vacuum oil filling, testing and packaging).Professional protective packaging, container loading documentation, and full technical support for installation and commissioning.

 

aktueller Firmenfall über [#aname#]  aktueller Firmenfall über [#aname#]

 

. Manufacturing & Quality Control Process


Design Confirmation: Drawing and BOM review per CSA standards and project requirements
Incoming Inspection: Full records for core steel, winding materials, insulation and oil
Production: CNC lamination, automatic winding, vacuum oil treatment and curing
Routine Testing:
No-load loss, short-circuit impedance, induced voltage, temperature rise, PD, sound level, moisture content, dielectric loss, etc., unit-by-unit recorded
Final Inspection & Packaging: Full function & visual check, export-grade reinforcement and moisture protection

 

aktueller Firmenfall über [#aname#]

 

. Conclusion & After-Sales Service


Winley Electric completed production and shipment of 153 CSA C2.2:06 compliant pole-mounted transformers within 7 weeks.Backed by UL/cUL certification, multi-voltage flexibility and strict quality control, Winley provides North American customers with high-efficiency, reliable and fully compliant solutions.
The delivery brings lower energy consumption, reduced maintenance, minimized compliance risk and clear environmental benefits.Winley continues to offer spare parts, technical consultation and responsive after-sales service for long-term project support.